Brussels Convention

Article 21

Untitled

Where proceedings involving the same cause of action and between the same parties are brought in the courts of different Contracting States, any court other than the court first seised shall of its own motion decline jurisdiction in favour of that court.

A court which would be required to decline jurisdiction may stay its proceedings if the jurisdiction of the other court is contested.

Holdings

/
C-39/0214 Oct 2004

Mærsk Olie & Gas A/S v Firma M. de Haan en W. de Boer.

1. An application to a court of a Contracting State by a shipowner for the establishment of a liability limitation fund, in which the potential victim of the damage is indicated, and an action for damages brought before a court of another Contracting State by that victim against the shipowner do not create a situation of _lis pendens_ within the terms of Article 21 of the Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters, as amended by the Convention of 9 October 1978 on the Accession of the Kingdom of Denmark, Ireland and the United Kingdom of Great Britain and Northern Ireland.

C-116/029 Dec 2003

Erich Gasser GmbH v MISAT Srl

2. Article 21 of the Brussels Convention must be interpreted as meaning that a court second seised whose jurisdiction has been claimed under an agreement conferring jurisdiction must nevertheless stay proceedings until the court first seised has declared that it has no jurisdiction.

C-116/029 Dec 2003

Erich Gasser GmbH v MISAT Srl

3. Article 21 of the Brussels Convention must be interpreted as meaning that it cannot be derogated from where, in general, the duration of proceedings before the courts of the Contracting State in which the court first seised is established is excessively long.

Skouris

Jann

Timmermans

Gulmann

Cunha Rodrigues

Rosas

Edward

La Pergola

Puissochet

Schintgen

Macken

Colneric

von Bahr

Delivered in open court in Luxembourg on 9 December 2003.

Registrar

President

C-351/9619 May 1998

Drouot assurances SA v Consolidated metallurgical industries (CMI industrial sites), Protea assurance and Groupement d'intérêt économique (GIE) Réunion européenne

Article 21 of the Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters, as amended by the Convention of 9 October 1978 on the Accession of the Kingdom of Denmark, Ireland and the United Kingdom of Great Britain and Northern Ireland and by the Convention of 25 October 1982 on the Accession of the Hellenic Republic, is not applicable in the case of two actions for contribution to general average, one brought by the of the hull of a vessel which has foundered against the owner and the of the cargo which the vessel was carrying when it sank, the other brought by the latter two parties against the owner and the charterer of the vessel, unless it is established that, with regard to the subject-matter of the two disputes, the interests of the insurer of the hull of the vessel are identical to and indissociable from those of its insured, the owner and the charterer of that vessel.

_

C-163/959 Oct 1997

Elsbeth Freifrau von Horn v Kevin Cinnamond

Article 29(1) of the Convention of 26 May 1989 on the Accession of the Kingdom of Spain and the Portuguese Republic to the Convention on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters must be interpreted as meaning that where proceedings involving the same cause of action and between the same parties are pending in two different Contracting States, the first proceedings having been brought before the date of entry into force of the Brussels Convention between those States and the second proceedings after that date, the court second seised must apply Article 21 of the latter Convention if the court first seised has assumed jurisdiction on the basis of a rule which accords with the provisions of Title II of that Convention or with the provisions of a convention which was in force between the two States concerned when the proceedings were instituted, and must do so provisionally if the court first seised has not yet ruled on whether it has jurisdiction. On the other hand, the court second seised must not apply Article 21 of the Convention on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters if the court first seised has assumed jurisdiction on the basis of a rule which does not accord with the provisions of Title II of that Convention or with the provisions of a convention which was in force between those two States when the proceedings were instituted.

_

C-406/926 Dec 1994

The owners of the cargo lately laden on board the ship "Tatry" v the owners of the ship "Maciej Rataj"

1\. On a proper construction, Article 57 of the Brussels Convention of 27 September 1968 on jurisdiction and the enforcement of judgments in civil and commercial matters, as amended by the Convention of 9 October 1978 on the accession of the Kingdom of Denmark, Ireland and the United Kingdom of Great Britain and Northern Ireland, means that, where a Contracting State is also a contracting party to another convention on a specific matter containing rules on jurisdiction, that specialized convention precludes the application of the provisions of the Brussels Convention only in cases governed by the specialized convention and not in those to which it does not apply.

2\. On a proper construction of Article 21 of the Convention, where two actions involve the same cause of action and some but not all of the parties to the second action are the same as the parties to the action commenced earlier in another Contracting State, the second court seised is required to decline jurisdiction only to the extent to which the parties to the proceedings before it are also parties to the action previously commenced; it does not prevent the proceedings from continuing between the other parties.

3\. On a proper construction of Article 21 of the Convention, an action seeking to have the defendant held liable for causing loss and ordered to pay damages has the same cause of action and the same object as earlier proceedings brought by that defendant seeking a declaration that he is not liable for that loss.

4\. A subsequent action does not cease to have the same cause of action and the same object and to be between the same parties as a previous action where the latter, brought by the owner of a ship before a court of a Contracting State, is an action in personam for a declaration that that owner is not liable for alleged damage to cargo transported by his ship, whereas the subsequent action has been brought by the owner of the cargo before a court of another Contracting State by way of an action in rem concerning an arrested ship, and has subsequently continued both in rem and in personam, or solely in personam, according to the distinctions drawn by the national law of that other Contracting State.

5\. On a proper construction of Article 22 of the Convention, it is sufficient, in order to establish the necessary relationship between, on the one hand, an action brought in a Contracting State by one group of cargo owners against a shipowner seeking damages for harm caused to part of the cargo carried in bulk under separate but identical contracts, and, on the other, an action in damages brought in another Contracting State against the same shipowner by the owners of another part of the cargo shipped under

the same conditions and under contracts which are separate from but identical to those between the first group and the shipowner, that separate trial and judgment would involve the risk of conflicting decisions, without necessarily involving the risk of giving rise to mutually exclusive legal consequences.

_

C-129/9220 Jan 1994

Owens Bank Ltd v Fulvio Bracco and Bracco Industria Chimica SpA

The Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters, in particular Articles 21, 22 and 23,

does not apply to proceedings, or issues arising in proceedings, in Contracting States concerning the recognition and enforcement of judgments given in civil and commercial matters in non-contracting States.

_

C-351/8927 Jun 1991

Overseas Union Insurance Ltd and Deutsche Ruck Uk Reinsurance Ltd and Pine Top Insurance Company Ltd v New Hampshire Insurance Company

1\. Article 21 of the Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters must be interpreted as applying irrespective of the domicile of the parties to the two sets of proceedings;

2\. Without prejudice to the case where the court second seised has exclusive jurisdiction under the Convention and in particular under Article 16 thereof, Article 21 of the Convention must be interpreted as meaning that, where the jurisdiction of the court first seised is contested, the court second seised may, if it does not decline jurisdiction, only stay the proceedings and may not itself examine the jurisdiction of the court first seised.

_

C-144/868 Dec 1987

Gubisch Maschinenfabrik KG v Giulio Palumbo

Lis pendens under Article 21 covers a case where one party seeks rescission or discharge of an international sales contract in one Contracting State while the other party's action to enforce the same contract is already pending in another Contracting State.